Olivia Grant

Olivia project

Active · 70% complete

70%
Contract sum
$34,000
Collected
$17,000
of $34,000
Est. completion
Jun 15, 2026
At risk
Open issues
0

Schedule

May 23, 2026Jun 15, 2026
Demolition
May 27, 2026
Framing
Jun 1, 2026
Rough-in (plumbing/electrical)
Jun 5, 2026
Drywall
Jun 10, 2026
Paint
Final walkthrough
On track Due soon Overdue Done Today

Completion timeline

Est. completion Jun 15, 2026At risk3/6 done
  1. DemolitionCompleteDone on time
    Due May 27, 2026· 2d· Reliable Framing LLC · $1,500· done May 26, 2026
  2. FramingCompleteDone on time
    Due Jun 1, 2026· 3d· done May 31, 2026
  3. Rough-in (plumbing/electrical)CompleteDone on time
    Due Jun 5, 2026· 4d· Precision Plumbing Co · $2,300· done Jun 4, 2026
  4. 4
    DrywallIn ProgressDue soon
    Due Jun 10, 2026· 3d· TopCoat Painters · $2,700
  5. 5
    PaintPendingDue soon
    Due Jun 12, 2026· 2d
  6. 6
    Final walkthroughPendingOn track
    Due Jun 15, 2026· 1d

Payments

  • $20,400
    To Precision Plumbing Co
    paid
  • $17,000 · 10% ret.
    From client · due Jun 18, 2026
    due
  • $17,000
    From client
    paid

Issues

Change orders